METAL BUILDINGS WALL SHEETING INSTALLATION (Con't.)
STEP 3
Begin sheeting the steel buildings sidewalls first. Plan the lap
so that it is not visible from the front of the steel building.
Start first sheet at corners with center of high rib in line with
edge of steel buildings line as shown. See next page for center
line starting point for first sheet.
It is very important that you use a level to plumb the wall
sheets while holding them in place by hand. When plumb run the first
two screws through the girt to hold the sheet in place.
Steel Building

Metal Buildings
APPLY SUFFIEIENT TORQUE TO SEAT THE WASHER
DO NOT OVERDRIVE THE FASTENER

|
|
|
| SEALING MATL. SLIGHTLY VISIBLE AT
EDGE OF METAL WASHER. ASSEMBLY IS WEATHER TIGHT. |
SEALING MATL. NOT VISIBLE - NOT
ENOUGH COMPRESSION TO SEAL PROPERLY. |
METAL WASHER DEFORMED - SEALING
MATL. EXTRUDED BEYOND EDGE OF WASHER. |