STEEL BUILDINGS WALL SHEETING INSTALLATION (Con't.)

STEP 5

Installing the eave flashing

Steel Buildings Eave Flashing

Metal Buildings

NOTE: When fastening the top of the eave trim to the eave strut, use 3 or 4 screws per 10' length of trim. Locate these screws in steel building line with a high rib, so .that when sheeting the metal buildings roof, the screw head will not obstruct the metal building roof sheet. Pop rivets are supplied to connect end laps of flashing together.

Steel Building
<-- previous page                                     next page -->

Steel Buildings Erection Manual Page1
Steel Buildings Erection Manual Page2
Steel Buildings Erection Manual Page3
Erection Manual Page4
Erection Manual Page5
Erection Manual Page6
Steel Building Erection Manual Page7
Steel Building Erection Manual Page8
Steel Building Erection Manual Page9
Steel Building Erection Manual Page10
Steel Building Erection Manual Page11
Metal Building Erection Manual Page12
Metal Building Erection Manual Page13
Metal Building Erection Manual Page14
Metal Building Erection Manual Page15
Metal Building Erection Manual Page16
Metal Building Erection Manual Page17
Metal Buildings Erection Manual Page18
Metal Buildings Erection Manual Page19
Metal Buildings Erection Manual Page20
Metal Buildings Erection Manual Page21
Metal Buildings Erection Manual Page22
Erection Manual Page23
Buildings Erection Manual Page24
Buildings Erection Manual Page25
Buildings Erection Manual Page26
Buildings Erection Manual Page27
Buildings Erection Manual Page28
Erection Manual Page29
Erection Manual Page30
Steel Building Erection Manual Page31
Erection Manual Page32

©ATY Steel Buildings